Boardman / Umatilla Data Centers and Infrastructure

What the public record shows about data center growth, electricity infrastructure, agriculture, and the sequence of development in northeastern Oregon.

What we know so far

Boardman’s data-center story reaches beyond the campuses. It runs through electrical lines crossing private land, roads serving industrial growth, tax-incentive agreements and water systems shared with agriculture and food processing.The records now document several parts of that story. Hermiston’s accounts record an Amazon contribution and a County-share expenditure. Morrow County adopted a paired industrial/agricultural land-use change. The Olson Road orders record a contested transmission route and property proceeding. The Tower Road materials identify a separate local turn-lane agreement. Those records answer different questions, and each needs its own place, date and scope.The earlier power timeline remains useful: data-center load requests preceded Morrow Flat’s public proposal, and BPA described a regional mix of demand. The later approvals and accounts add the decisions, obligations and property interests around that growth.Water needs the same care. The Lower Umatilla Basin nitrate problem was recognized in 1990, long before the major data-center buildout. Port and DEQ records establish a shared industrial wastewater system, but the records reviewed here do not trace a named data center’s wastewater to a particular field and measured agricultural effect.I am following how new demand fits into systems that farms, food processors and communities already use, and what the records establish about the benefits, obligations and changes along the way.

Infrastructure

Boardman’s industrial growth shares electricity, land and water systems with agriculture, food processing and existing communities. The records need to be read at both regional and facility scale.ElectricityBPA’s early load requests identify PDX-1 and PDX-4. Its August 8, 2014 environmental clearance memorandum, page 1, describes Morrow Flat improvements intended to serve up to 250 MW of regional load growth from existing development, food processors and new data centers. That is a proposed regional planning figure, not measured electricity use or an allocation to one company. The timeline below gives the sequence. These records do not establish each customer’s share or PDX-4’s original feeder.Water and wastewaterState drinking-water records identify groundwater systems associated with Amazon Data Hermiston PDX080 and Amazon Data Umatilla PDX063. Those records establish a source type, rather than campus withdrawal or consumption totals.Port and DEQ records identify data-center cooling water in the Port of Morrow’s shared industrial wastewater system. That system is permitted to land apply industrial wastewater. A source called VA Data #4 is identified as cooling-tower blowdown; its exact facility identity remains unresolved. It should not be equated with PDX-4 without a supporting record.The shared system does not, by itself, establish a dated route from a named data center to a particular field or an effect on crops or groundwater.Port of Morrow’s December 2022 permit statement describes the shared system. Its upgrade plans are historical statements, not confirmation of completed work.Oregon’s 2024 Nitrate Reduction Plan, section 4.5 supplies the regional land-application context.LandBPA’s November 2013 public proposal described a 17.5-acre substation. Its August 2014 memorandum, page 1, described developing approximately 22 acres of industrial-zoned land formerly in agricultural production. These are dated descriptions of the proposed project scope, not measurements of the final area paved or removed from cultivation. They do not measure the region’s overall agricultural production loss.

More recent findings: payments, land, power and roadsThis regional case includes Hermiston in Umatilla County as well as Boardman in Morrow County. The records now answer more than the early Morrow Flat timeline. They show a recorded company contribution, a change in tax-exemption qualification terms, an adopted land-use exchange and a later regional substation.A $5 million contribution appears in Hermiston’s accountsHermiston’s FY2026–27 adopted budget includes historical FY2023–24 actual results for its Greater Hermiston Enterprise Zone Project Fund. They record $5 million as “Contribution from Amazon” and $2.5 million as “County Share of Amazon Contribution.”The zone manager’s report identifies a $5 million Community Development Contribution for PDX245 and describes an equal City/County split. Read together, these records support the contribution and the allocation. They do not show that the entire $5 million was available for the City’s own projects, or that the remaining City share is still unspent. The County-share entry is a City expenditure record, not the County’s deposit record.Hermiston FY2026–27 adopted budget, printed page 132 / PDF page 138
Zone manager’s report, printed pages 7–8 / PDF pages 50–51
The investment and employment thresholds changed togetherHermiston’s February 13, 2023 staff reports for the PDX245 and PDX146 amendments explain a switch in qualification routes: the initial investment threshold would fall from $200 million to $12.5 million, while minimum employment by the third year of operation would rise from ten to fifty full-time employees.That is a change in qualification terms, not evidence that employment requirements disappeared. It is also not a current job count or proof of compliance. The investment threshold is not a ceiling on what a campus may ultimately cost.February 13, 2023 council packet, staff reports at PDF pages 76–77 and 83–84The land-use change ran in both directionsMorrow County lists Ordinance 2025-02 as adopted July 16, 2025. It changed a roughly 1,298-acre tract from a mixture of Agricultural and Space Age Industrial designations to Industrial, with an overlay limiting uses to data centers and farming. The same ordinance changed a separate roughly 1,623-acre tract from Space Age Industrial to Agriculture/Exclusive Farm Use.Both sides belong in the account. These are land-use designation areas, not a measurement of acres actually paved, cultivated or lost from production. The ordinance alone does not establish a sale, sale price or change in agricultural output.Signed Morrow County Ordinance ORD-2025-02, pages 1–3The electrical buildout continued after Morrow FlatBPA announced Longhorn Substation’s energization in April 2025. Its description identifies a multipurpose regional facility: connections for Umatilla Electric Cooperative’s current and future customers, as well as approximately 2,500 MW of new generator interconnections.The 2,500 MW figure describes generator interconnection capability, not Amazon’s electricity demand. Longhorn should not be presented as an Amazon-only project, and its existence does not establish who ultimately paid each part of the wider buildout.BPA’s April 17, 2025 Longhorn announcementThe electrical buildout also crossed private propertyThe Olson Road transmission proceeding puts a different part of the infrastructure story on the record: the route across land, and the process used to approve it.On March 5, 2021, Oregon’s Public Utility Commission granted Umatilla Electric Cooperative a certificate for a proposed 4.3-mile, 230-kV line from the planned Highway 730 switchyard to a planned substation near Olson Road. The order records landowners’ objections to routing, agricultural effects and whether the line served a narrow customer interest. UEC argued that reliability needs justified the project. The Commission found the line necessary and justified and granted the certificate.PUC Order 21-074: route, objections, utility response and decisionA later land-use appeal supplies a more specific property history. LUBA’s October 13, 2022 opinion identifies 1st John 2:17 LLC as the owner of property the line would cross, with Jonathan Tallman as its managing member. It records a July 2021 condemnation filing and an October 2021 advance-occupancy order. It also says funds were deposited with the court and later withdrawn by the property owners.LUBA affirmed the City’s installation approval in case 2022-029. That decision is not a final compensation accounting, proof of voluntary easement consent or a finding that the line served Amazon exclusively. The record establishes a contested route and property proceeding; the final financial outcome requires separate records.LUBA 2022-029: factual history at PDF pages 3–5; disposition at page 2Tower Road: one local turn lane is a different project from the interchangeThe County’s August 19, 2026 minutes record approval of an Amazon Data Services road-improvement agreement providing reimbursement up to $375,000. The packet copy describes a temporary right-turn lane from southbound Tower Road into Bristow Lane, with County construction and ADS reimbursement. Its cap includes design, engineering, inspection and administration.That is a defined local improvement. It should not be confused with the broader Tower Road interchange plan, the electrical project sharing the Tower Road name, or a payment already received.The agreement copy reviewed has blank signature and date blocks and makes effectiveness depend on all parties signing. Approval is documented; execution, invoices, payment and completed construction are not established by that copy. I am keeping those stages separate so a promised contribution does not become an assumed receipt.County August 19 approval minutes, printed pages 3–4
Tower Road Improvement Agreement: unsigned packet copy
These findings make the question more specific. Some contributions and obligations can be documented. Regional infrastructure still needs to be separated from individual facilities before assigning its entire cost or capacity to one company. I am keeping the project, place, year and type of record attached to each number.

What happened when

1990
The Lower Umatilla Basin is designated a Groundwater Management Area because of elevated nitrate levels.
2011–2012
BPA’s interconnection queue spreadsheet records Umatilla Electric Cooperative’s 60 MW “PDX1&4 Data Centers” request (L0342) on December 13, 2011, followed by its 225 MW “PDX-1 and PDX-4 Data Centers - Phase 2” request (L0351) on August 3, 2012. The listed interconnection points are Boardman and Morrow Flats Substation, respectively. These are separate planning requests; their capacities should not be added together or treated as measurements of delivered load.
2013–2014
PDX-4 is operating by 2013. BPA publicly proposes Morrow Flat in November 2013; its August 8, 2014 environmental clearance memorandum describes the proposed improvements. These planning documents do not establish an exact in-service date. The queue reviewed on October 23, 2026 lists both requests as ENERGIZED, but its requested and agreed in-service dates should not be treated as proof of actual energization.
2021–2022
The PUC grants the Olson Road transmission certificate. The later LUBA opinion records the property proceeding and affirms the City’s installation approval. See the linked orders above.
2023–2024
Hermiston’s staff reports explain qualification changes. FY2023–24 accounts record the Amazon contribution and County-share expenditure discussed above.
2025
BPA announces Longhorn’s April energization. Morrow County adopts the paired industrial/agricultural designation change on July 16.
August 19, 2026
County minutes record approval of the separate Tower Road turn-lane agreement. The reviewed packet copy does not establish execution or payment.

What remains unresolved

The remaining questions concern connections between records: PDX-4’s original service path; final infrastructure costs and customer shares; VA Data #4’s facility identity; and dated wastewater routes, quantities and composition.The regional nitrate problem predates the data-center buildout. Testing a later contribution or agricultural effect requires a named source, a pathway, a relevant year and measured outcomes. Proximity and shared infrastructure cannot establish that chain on their own.The documented payments, approvals and land changes above stand on their own. They should not be treated as proof of the unresolved water or cost-allocation claims.

Sources & primary records

Most of what I am using for this case study comes directly from public records.Some of the most useful records so far have come from:Bonneville Power Administration (BPA)Transmission planning, load requests, outage records and project documents are helping me piece together when electrical demand showed up and what infrastructure followed.Morrow Flat public proposal, November 2013
The early description specifies a 17.5-acre substation.
BPA interconnection queue — original spreadsheet
Search request IDs L0342 and L0351 for the 2011 and 2012 PDX-1/PDX-4 requests. Reviewed October 23, 2026. Requested capacity and proposed or agreed dates do not establish measured consumption or actual energization dates.
Oregon Department of Environmental Quality (DEQ)DEQ records have helped establish when individual facilities were operating and how they were regulated.Amazon PDX-4 Data CenterDEQ records are also important for understanding the groundwater issue and the nitrate problem that predates the major data center buildout.Lower Umatilla Basin Nitrate ContaminationOregon Groundwater Management AreasU.S. Department of EnergyBPA’s August 8, 2014 environmental clearance memorandum describes proposed Morrow Flat improvements. Page 1 identifies up to 250 MW of regional load growth and approximately 22 acres of industrial-zoned land formerly in agricultural production. These are planning-scope figures, not a company-specific electricity allocation or an as-built acreage measurement.Morrow Flat environmental clearance memorandum — original PDF, page 1Department of Energy record and document landing pagePort of MorrowPort and DEQ records are helping me trace the wastewater side of this story, including data center cooling water wastewater, the Port's industrial wastewater system and land application on agricultural land.Umatilla Electric Cooperative (UEC)UEC information is part of figuring out the local electrical system, how individual data centers were connected and how new infrastructure costs were divided.There are still records I am waiting on, especially the ones that could answer some of the harder questions about who paid for infrastructure, how individual facilities were connected, and how much water is actually moving through these systems.As those come in, I'll add them here and update the findings when they change what we know.Port of Morrow: December 2022 statement on its modified permit
This is a historical description of a shared industrial system, not a facility-to-field routing record or confirmation that every announced upgrade is complete.
Oregon Nitrate Reduction Plan, September 2024
Section 4.5 addresses industrial and domestic wastewater land application. It provides regional context, not proof that a named data center caused a particular crop or well impact.
Browse the Sources page · Get the free community guide

About this case study

I follow records across agencies to understand how data-center growth fits into an agricultural region. I update findings when new evidence changes the picture, and link original records where available.Reviewed October 23, 2026. Includes the Hermiston contribution and qualification terms, land-designation exchange, Longhorn, the Olson Road property proceeding and Tower Road turn-lane approval. The BPA queue and Morrow Flat planning figures have also been checked against the original records. Approval, payment and measured effects remain distinct.Clouds on the Range is an independent research project examining data centers, agriculture, water, energy, infrastructure and rural communities.